Milestones

  • Andover Road - Phase 1

    April 2021

     

    -

     

    June 2021

    Concept design and initial consultation
  • Andover Road - Phase 2

    September 2021

     

    -

     

    February 2022

    Feasibility design and further consultation
  • Andover Road - Phase 3

    March 2022

     

    -

     

    June 2022

    Detailed design
  • Andover Road - Phase 4

    July 2022

     

    -

     

    August 2022

    Civil engineering construction - alterations to kerblines, layby and bus stop, prior to road resurfacing, lining and signing